1.TOTAL GUARDING PROJECT
2.TOTAL ISOLATION PROJECTS
Also see: SAFETY ISOLATION LOCKOUT SYSTEMS
Note: Vertical integration between the above subjects provides a safer management system
Total guarding project proposal
Total Guarding of the machinery project for a Site
What we would be proposing:
Commit to the upgrading of the guarding and electrical safety interlocks on the existing equipment.
This work includes hazards assessment of the motors, hydraulic and pneumatic actuators that power the machine’s moving parts and assigning a CAT rating in line with AS 4024 and design of the appropriate controls. The control philosophy is to allow the operator to stop the part of the machine that he wishes to access using normal controls. The operator would then verify that the machine is safe to enter, open an isolator and fit his personal lock. This action will release the electromechanical lock on the guard. Secondary protection is provided to detect if the guard lock is overridden.
Why it would be proposed:
Known incidents including the near miss and injuries i.e. SSO.
The proposal is to address root causes in all of the incidents. The back-ground history of when the machinery was installed in at the site. The additions and modifications to the machinery over the years. Rapid changes in electronic technology will continue to generate needs to regularly review control hardware and software.
The machine may have many interlocked guards installed and these may have been upgraded on an ad hoc basis to cover more and more of the machinery over the a few years.
The machine may be complex to set up and with significant operator interaction with the machine. The incidents may have identified that the current guarding interlocking and isolation systems are inadequate in that:
The benefits:
The number of operational conditions would be assessed and risk ranked. The highest risk will be reduced to less than 4.0 at completion of the project.
Financial benefits will be calculated from the costs of SSO’s
The background
The current machinery assets requires the guard system to be upgraded to AS 4024.1-2006
The machinery has been assessed and a number of reports tabled.
The reports could be complied by the Lead Mechanical Engineer for the company
From the review by an assessment team i.e. Managers and supervisors.
Or by an assessment of all the tasks observed by the safety engineer i.e. an each task risk assessed both production and maintenance tasks.
The tabled information would be:
Funding
Could be based over a period and on a capital application of $
Labour $ (65%)
Goods $ (25%)
Inconveniences $ (10%)
Note: Goods & labours estimates would be via spreadsheet
The expertises
Engineering persons with previous Guarding system design & implementation experiences will complete the project.
The Prerequisites for the persons are:
Basic knowledge of site and process
Has been trained in Protected person, Isolating person, Isolation planner and is an advanced contractor controller.
The plan
The plan would be based on working from the recommendations of tabled reports
An electrically intergraded system complimented by some mechanical guards would be designed and installed on the production line.
Design
Other milestones:: Building, Cold commissioning, Installation, Hot Commissioning, Documents, Training of personal, System maintenance.
Not considered is the Total isolation of any assets, this would be subject to a separate project plan
A proposal total isolation system for a site would consider the following points:
The background
The industry & current site’s assets that require the Total isolation system
The expertises of an experienced isolation systems person
An engineering person with previous Total isolation system implementation experiences will complete the project.
The project plan would consider and address
Not considered is the Total guarding of any assets, this would be subject to a separate project plan
Example: Library of Total isolation plans, location of isolator plans and isolation matrixes using the safety isolation lockout systems